Santa Venetia Floodwall Facts
Independent, plain-language information for the ~600 homes in the flood zone

How we got here: 2018–2026

Every entry below is drawn from a public document — county press releases, board letters, budget documents, and published news coverage. See Key Facts & Documents for the sources.

The pattern: the cost has gone from $6 million to $25–30 million — a four- to five-fold increase — with zero construction to show for it. The constant through every delay is the easement problem: the design requires a permanent 18-foot easement on 111 private parcels, and five years of effort has produced 16 signatures.

See the documents behind this timeline →